National Australian Pipelines were engaged by APA Group to construct approximately 62m of DN300 steel gas pipeline relocation, and decommission approximately 60m of the existing pipework which will be impacted by the construction of the Riverlee Development, South Melbourne Victoria.
The relocation of the pipeline is required due to the future impact the Riverlee development will have on the typical cover of the existing asset during construction.