National Australian Pipelines were engaged by Lochard Energy to construct two new pipelines, connecting to the North Paaratte Production Station, near Port Campbell VIC.
The Iona Gas Plant (IGP) operated by Lochard Energy located near Port Campbell in south-west Victoria required several stages of upgrades which aim to increase plant capacity. Phase 3 of Project 570 was undertaken to upgrade the gathering line network that connects North Paaratte and Wallaby Creek to Iona.
Works included; Construction and Installation of approximately 4.85 km of DN300 Pipeline and approximately 0.5 km of DN50 MEG Pipeline. Along with laying of approximately 5.35 km of Fibre Optic Cable and installation of 0.5 km of two 240V power supply cables in a common trench as the newly installed pipeline.