National Australian Pipelines were engaged by APA Group to construct approximately 250m of DN100 steel gas pipeline extension to supply 691 Collins St, Melbourne Quarter Building.
The DN100 pipeline was designed and constructed in accordance with AS4645 for distribution services.
The new service is approximately 250m long installed parallel to the existing APA Transmission Pressure assets located along Flinders St, Melbourne.
Hot tap connection was completed to the existing APA asset through 3 way sit on tee and commissioned in preparation for construction of the new Melbourne Quarter Building.
All works were completed utilising conventional open cut trenching along Flinders St, Melbourne.