Transmission Gas Duplication Main, Mornington-Tyabb Road

Project Date

2007

Length

5.4 kms

Pipe Diameter & Type

200mm Steel Pipe

The Tyabb Transmission Gas Duplication Main involved construction of 5.4 km’s of 200mm Steel High Pressure Transmission Pipeline along the Mornington – Tyabb Road.

The Tyabb Transmission Gas Duplication Main involved construction of 5.4 km’s of 200mm Steel High Pressure Transmission Pipeline along the Mornington – Tyabb Road.

Major activities

Major activities undertaken for this project included:

Pipelaying along Mornington Tyabb Road.
Non destructive testing of welded joints.
Pipelaying under power lines with spotters.
Traffic management to VicRoads standards.
Contra flow set-up along VicRoads managed roads using temporary traffic lights.