This project involved the construction of 200m of 1200mm Mild steel pipeline at the Essendon Airport.

This project involved the construction of 200m of 1200mm Mild steel pipeline at the Essendon Airport.

Major activities

Major activities undertaken for this project included:

Fabrication and construction of mild steel (15 Tons) tie-in assemblies.
Bulk excavation and concreting works for Freeway construction.
Timely completion was essential to enable Freeway construction.
Co-ordination with Melbourne Water and Baulderstone Hornibrook to ensure that the shutdown time for tie-in was acceptable and achievable by all parties. Melbourne Water gave us 36 hours to do the tie-in, but we completed it in 24 hours.