Dromana Reservoir Bypass Main

Client :

Melbourne-Water

Project Date

2004

Length

800m

Pipe Diameter & Type

960mm MSCL

This project involved the construction of 800m of 960mm mild steel pipeline for the Dromana Reservoir Bypass main (for Melbourne Water).

This project involved the construction of 800m of 960mm mild steel pipeline for the Dromana Reservoir Bypass main (for Melbourne Water).

Major activities

Major activities undertaken for this project included:

This project also involved extensive amounts of pipefitting and fabrication to tie-in to the existing structure.
Co-ordination with Melbourne Water and Yarra Valley Water to ensure that the shutdown time for tie-in was acceptable and achievable by all parties. Melbourne Water gave us 6 hours to do the tie-in, but we completed it in 4 hours.